Completed Projects

Completed Education 2010 PPP Projects

As of 20 October 2008, allseventeen Education 2010 PPP projects are now occupied.

(The only construction remaining is the construction of new playing fields - go to Construction Progress to view progress).

?The three secondary school projects, Airdrie Academy, St Andrew's High School whichincludes a sports complex and Community Centre, and the new Coatbridge High School.

?The fourteen primary school projects, 7 being joint campus projects in Bargeddie, Caldercruix, Chapelhall, Glenboig, New Stevenston (New Stevenston includes a public library), Plains and Wishaw and 7 are single school projects inCambusnethan, Clarkston, Coatbridge,Kilysth, Stepps (including a cultural centre), Tannochside and Viewpark.

The details for each are provided below in date order:

20 October 2008

Coatbridge High School is completed and occupied on time.

6 October 2008

Clarkston Primary and nursery is completed and occupied 2 weeks early.


10 December 2007

Bargeddie and St Kevin's Primary schools and nursery joint campus is completed and occupied 6 weeks early.

Glenboig and Our Lady and St Joseph's Primary schools and nursery joint campus is completed and occupied 2 weeks early.

12 November 2007

Stepps Primary school , nursery and Cultural Centre is completed and occupied.

5 November 2007

Plains and St David's Primary schools and nursery joint campus is completed and occupied 2 weeks early.

20 August 2007

Cambusnethan Primary School and new nursery is completed and occupied on time.

St Ignatius and WishawAcademy Primary Schools and nursery joint campus is completed and occupied on time.

St Patrick's Primary School, Kilsyth and its nursery is completed and occupied on time.

23 October 2006

St Andrew's High School is occupied with its 1 stbuild phase completed on time. The 2 ndphase to demolish RosehallHigh School in order to complete the grass pitches will not commence until Rosehall pupils move into their new secondary school in 2008.

Airdrie Academy is occupied with its 1 stbuild phase completed on time. The 2 ndphase to demolish the old school to complete all the pitches, bus drop off and finalise the landscaping is in progress.

21 August 2006

Tannochside Primary school was fully occupied on time and the 2nd phase finishing works have now been completed (8 Mar 2007).

New Stevenston and St Patrick's Primary joint campus and public library is completed on time with the schools taking full occupation. The next phase to demolish the old school so that the car parking and landscaping are in place have also now been completed (24 Feb 2007).

18 August 2006

Chapelhall and St Aloysius Primary joint campus is completed and occupied.

22 May 2006

St Timothy's Primary school completes and occupied on time.

1 May 2006

John PaulIIPrimary school completes and occupied on time.

23 January 2006

Glengowan and St Mary's Primary joint campus is the first of the Education 2010 PPP projects to complete and be occupied on time.