M6 Junction 35 Electronic Message Signs and CCTV

Project status:   Completed
Region:  North West

Start date:   24 November 2014
End date:  31 March 2015

Type:   Improvement Scheme
help icon

Improvement Scheme

Part of our programme of improvements (generally with value <£10m)

Cost:  £2 million

Managed by:   Area 13


Where was the project located?

The scheme is located on the M6 in the area of junction 35 near Carnforth, Lancashire.

Why was the scheme needed?

The scheme was needed in order to provide relevant and up-to-date information to drivers about road conditions either local to the M6 or more strategic to the larger network, electronic message signs are being erected.

What work was carried out?

Electronic Message Signs have been provided at one mile and half a mile in advance of junction 35 on both the north and southbound approaches.

How did this benefit road users?

As part of the pinch point programme, this scheme will help to reduce daily congestion, reduce journey times for the travelling public, boost the economy and improve safety.

How do I find out more information ?

If you have any queries about this project you should contact the Highways Agency Information Line by emailing ha_​info@​highways.​gsi.​gov.​uk or calling 0300 123 5000.