Ellon

(TotalFinaElf)

Offshore gas and condensate field in production.

Block and licence number:

3/15, P.090

Map reference:

Plate 6

Grid reference:

1° 49’ E 60° 36’ N

Licensees and company interest in field (%) at end of February 2002:

TotalFinaElf Exploration UK plc

33.33

Elf Exploration UK plc

66.67

Date of discovery:

October 1973

Production start:

December 1994

Operator’s estimate of:

 

Recoverable reserves originally present (billion cubic metres):

Gas: 3.79

First year of peak production:

1996

Peak production (billion cubic metres per year):

0.90

Water depth:

135m

Transport system:

Pipeline to St. Fergus via Alwyn and Frigg.

Extension into other UK blocks:

Block number, licence number and licensee/company interest in block (%) at end of 2000:

3/14a, P.090

TotalFinaElf Exploration UK plc

33.33

Elf Exploration UK plc

66.67