E.5 CONTRACT STRATEGY
E.5.1 Contents
Introduction
Contractual approaches
Contract Types
- Cost
Reimbursement Contracts
- Fixed Price Contracts
- Capped Price Contracts
- Incentive Contracts
- Framework Contracts
- Stage Payment (Milestones)
- Single or Competitive Tender
E.5.2 Introduction
The advice in this section should be read in conjunction with the guidance
available in the OGC's Successful
Delivery Toolkit (external link verified June 2004)and in particular the guidance within the
Requirements Definition and Procurement Strategy (external
link verified June 2004) section of this document.
For all procurements over £10,000 in value it is important to determine the
most appropriate contract strategy before proceeding to issuing an invitation
to tender.
The contract strategy should take into account the following elements:
- how the various stages of the contract (from setting the strategy, right
through the various steps to contract management) are to be managed,
- options for procurement - purchase, rent, hire, etc.,
- contractual approaches and types of contract to be used,
- basis of pricing and payment arrangements,
- use of single or competitive tender,
- conditions of contract,
- the impact of Intellectual or Industrial Property and
associated rights (see Section D.4 - UK
Legislation)
The contract strategy should also take into account relevant aspects of DTI
policy, such as:
- policy on the environment (see Section A.7 -
Environmental Issues in Purchasing)
may affect the way a specification is prepared (defining the product and selecting
appropriate standards)
- policy on small firms (see Section A.6 - Small
and Medium Enterprises)
may affect the make-up of the list of companies invited to bid for work and
the way a contract is broken into lots (to enable small firms to bid)
- EU Directives (see Section E.8 - European Union
Directives), remembering also that
- the possibility of contract renewal needs to be taken into account in
assessing the value of a contract for EU procurement threshold purposes
and
- R & D procurement can fall within the scope of the EU Services
Directive if the Department is retaining intellectual property rights.
The contractual approach and type of contract selected must be appropriate
to the procurement. A range of factors needs to be considered, including:
- Departmental policy (see above)
- allocation of risk (see Section E.6 - Gateway
Reviews)
- in-house resource availability (e.g. for design and project management)
- importance of timescales
- project complexity and size
- importance of precise requirements and quality
- availability of funding
- availability of standard design or component detail
- market conditions
- lifetime costs.
The paragraphs below describe various contractual approaches, contract types
and payment arrangements. Bear in mind that the
choice of contractual approach, contract type and basis of payment should represent
an appropriate balance between cost, time, control and risk.
E.5.3 Contractual Approaches
In many cases, procurement is a relatively straightforward process.
Once the business case has been approved, the end user creates the specification
and the procurement staff identifies a suitable supplier and places
a contract. However, not all procurement can be effectively managed in
this way. For more complex projects it may be appropriate to consider
placing a management contract and/or undertaking sequential tendering.
- Management Contracts
For large and complex projects (typically major works projects
but also increasingly for the procurement of a range of contracted-out
services) it may be appropriate to award a contract to a specialist
contractor to manage the breakdown of the project into suitable packages,
to supervise the whole process of tendering for these packages and
possibly also to manage the contracts once awarded.
Such an approach can be very effective when specialist contract management
skills and knowledge are needed. However, care needs to be taken to
ensure that the Department retains sufficient intelligent customer
capability to be able to manage the appointed management contractor
effectively.
- Sequential Tendering
Where a project or requirement is too complex to be covered by a fully pre-planned
contract, sequential tendering is an alternative.
The overall project is broken down into a series of smaller packages
each of which is competitively tendered as and when the detailed requirements
are known. This approach should lead to a shorter overall time-scale than
a fully pre-planned approach and can provide a better fit to your requirements
by leaving some of the detailing until later in the process. This can
be particularly important where rapid technological change is envisaged.
A major disadvantage of this approach is that the overall cost remains
an estimate until the last package contract is awarded.
This factor is particularly important in obtaining overall approval for the project,
as approval authorities tend to prefer strategies with
a single decision point and closer control over total cost at the outset.
This disadvantage is also of relevance to projects that approach the EU
Directives thresholds and care should be taken in such circumstances that
sequential tendering does not become improper disaggregation.
E.5.4 Contract Types
There are a number of contract types to choose from. Those most likely
to be encountered by DTI procurement staff are:
- Cost-Reimbursement Contracts (time and materials); Cost Plus Contracts
Cost-reimbursement contracts are those in which the contractor is
reimbursed for the cost of labour and materials actually used in the
contract, plus a fee for supervision, head office expenses and profit.
The fee may be a fixed amount or a percentage of total prime cost.
Cost-plus contracts may be appropriate if the work is
very urgent or if it is hard to decide how much work is required.
However, as there is no risk to the contractor and no financial
incentive to work efficiently or to seek ways to save money, it can
be difficult to ensure that best value for money is obtained. They
should, therefore, be avoided whenever possible.
- Fixed Price Contracts
These are considered to be the most effective type of contract. They benefit
both parties. They give an efficiency incentive to the contractor and the Department knows
from the total cost from the outset.
A fixed price contract is one where the Contractor bids a fixed price
for undertaking the work. This is usually shown as a single sum, rather
than as a day rate with a total number of days. Such a sum will be clearly indicated
in the contract. The Contractor is then bound to satisfactorily complete the
task for this quoted sum. He assumes the risk for failing to do, but equally
will benefit if he can complete it within his own estimated timescale.
Fixed price contracts are of two main types:
- Lump Sum Contracts and
- Measured Contracts.
In lump sum contracts, a single total price (the lump sum) covers the whole
contract. This is considered suitable for major works if they can be precisely
defined and described in detail in the contract documents, and also for minor
works and alteration and repair jobs. However, fixed price contracts can be
applicable in a range of circumstances when the scale and nature of a procurement
can be clearly defined in advance.
In measured contracts, price is fixed in the sense that bidders quote itemised
prices for doing work and supplying materials, using a bill of quantities, but
the total price payable is determined by measuring the amount of work done and
materials supplied, multiplying by the agreed price for each item and totalling.
- Capped Price Contracts
These will be the most familiar types of contracts found in the Department,
particularly for procuring professional and consultancy services.
They are similar to cost re-imbursement contracts, in that a daily
fee is agreed at the outset. However, the fee will include any
profit element and the total number of days will also be fixed at
the outset.
Such a contract will be along the lines of, as an example, "£400
per day at a maximum of 20 days" and, in this example, is capped
at £4,000 for the total contract price. This cap must be clearly indicated
in the contract/purchase order. If the contractor is able to complete
the task within the stipulated number of days then his bill will be
less than the capped amount. If, however, he needs additional days
to complete the task, he has to make the case for the cap to be increased.
There may be good reasons for so doing, but they need to be investigated,
and the reasons for extending the cap recorded.
Contracts should never be let solely on the basis of an agreed daily
(or other period) fee, without including a cap on time or cost.
- Incentive Contracts
Incentive contracts give the supplier an incentive for success. They
have been widely adopted in the construction industry as an alternative
to cost plus contracts in cases where the cost can be estimated roughly,
so that a figure for target cost can be agreed, but not with sufficient
accuracy to arrive at a fixed contract price. They are intended to
motivate a supplier to achieve target cost by sharing with them any
savings they manage to make, while obliging them to stand part of
the expense if costs are above target.
Multiple incentive contracts extend this by including in the contract
monetary incentives for achieving other targets, such as delivery
performance and quality performance (e.g. customer satisfaction).
With multiple incentive contracts, there can be a problem balancing
one desirable objective, such as high performance, against another
desirable objective, such as early delivery or low prices. Care needs
to be taken in setting and balancing the monetary rewards embodied
in the incentive clauses to ensure the contractor optimises on a balance
of objectives which is in the Department’s interest rather than his
own.
- Framework (Call-Off) Contracts
Framework, or call-off, contracts set the terms on which
the Department will make future purchases of supplies or services. For details
on the use of such contracts see Section E.9 -
Frameworks.
f. Stage Payments ("Milestones")
Payments can only be made when goods or services have been satisfactorily
supplied in accordance with the terms of the contract. For straightforward
purchases this will mean payment on satisfactory completion of the contract.
For some contracts it can be appropriate to agree payment at predetermined
stages, often referred to as "milestones". This can also be
used as an alternative to regular re-measurement of the quantities of
work and materials expended or the percentage completion level of a contract.
By setting various "milestones" along the path towards completion
of a contract the need for re-measurement is avoided and payments can
be tied to stages of partial completion. Careful selection of "milestones"
can also be used to minimise risk to the DTI by ensuring that payment
is only made at stages where it would be feasible for a contract to be
taken over by another contractor, if necessary.
g.
Single or Competitive Tender
Competitive tender is the normal method by which DTI lets its contracts. Single
tender action (STA) should be the exception, particularly for contracts over
£10,000 in value. It can be more difficult to demonstrate that value for money
has been obtained when STA is used and there are increased risks of accusations
of impropriety.
The exceptional circumstances that may make STA permissible, include:
- no alternative sources of supply
- procurement need can be met only by proprietary or specialist equipment
- continuing the use of specialist professional services (but only once)
- for technical reasons
- supplier offering an innovative product or service
- private sector financing the major part of the work.
Shortage of time in itself is not normally adequate justification for STA.
This is particularly so where it is proposed to renew a supply or continue a
service, because there should have been ample opportunity to plan for the contract
to be re-tendered.
STA can be justified as a means of extending a contract (not already containing
specific provision for extension) where an imminent policy change or an unavoidable
delay in re-tendering would otherwise result in the interruption to an essential
service or supply.
STA should be used only once to extend or re-let a contract. In addition to
value for money considerations, re-letting contracts by STA further increases
the risk of accusations of impropriety.
STA is subject to more rigorous scrutiny than competitive tender, so you should
ensure that:
- you allow adequate time (it may actually take longer in the end if you have
to demonstrate that a competition cannot be held)
- you try to locate alternative sources of supply before using STA
- your case is fully justified in accordance with the criteria laid down
- you do not disclose to the supplier that he is the only tenderer.
The justification for STA must be put in writing, approved by the budget holder
and placed on file for audit purposes. It is also good practice for Directorates
to monitor closely the overall extent of the use of STA.