E.16 PAYMENT
E.16.1 Contents
Prompt Payment
Invoice Payment and Control including Receipting Goods or
Services.
Responsibilities
Payment Due
Payment in Advance
Miscellaneous
Additional Payments
E.16.2 Prompt Payment
DTI is committed to 100% achievement
of the promise in the DTI Standard Terms and Conditions
of Contract for Supplies and for Services to pay within
30 days of presentation of a correct invoice. See also Section
B.2.3.
CSL Managed Services in Newport processes DTIs payments
within 2 days of receiving payment authorisation.
E.16.3 Invoice
Payment and Control
including Receipting Goods or Services.
All purchases of goods and services, except those for petty
cash, must be the subject of a purchase order or an offer
of contract (in relation to which a purchase order has been
raised). The supplier must quote the purchase order or contract
reference on their invoices.
End users should be responsible for the manual receipting
of the goods received note, after satisfying themselves
that the goods or services have been provided. The budget
holder should not carry out this task. It is important to
enter such receipting onto the OPC system. This can be done
by the purchase order entry officer.
On receipt of an invoice the invoice entry officer will
need to check that the purchase order it refers to has been
quoted. They will also need to check that the invoice can
be matched to all or part of the purchase order and that
the goods or services have also been receipted. The invoice
details are then entered into the OPC system.
Matching of the invoice to the purchase order takes place
on-line. This will generate a payment authorisation, which
must be checked. It is then signed by the invoice entry
officer as first signatory and sent to the financial authoriser
as second signatory. The signed payment authorisation is
forwarded to CSL for approval and payment.
E.16.4 Responsibilities
Responsibility for processing invoices normally rests with
end users, project managers and other receiving officers
although purchasers may also process invoices. Wherever
the responsibility lies, there should be a clear separation
of duties between authorising the commitment to incur expenditure,
placing the purchase order or awarding the contract, certifying
performance of the service or acceptance of the goods and
authorising payment.
Managers are responsible for ensuring
robust procedures are in place to provide an effective separation
of duties and a complete management trail linking order,
receipt and payment. The instructions contained in Accounting
Memorandum 2.5, Finance Handbook chapter 2.1.12 and 2.1.13,
and Government Accounting chapter 31.1.5 should be followed.
(See also Part B
on Accountability and Standards
of Conduct.)
E.16.5 Payment
Due
Where goods have been supplied at DTIs request, payment
for them is due unless they can be rejected, e.g. because
they are faulty. If goods have been wrongly supplied or
supplied without DTIs consent, no payment is due but the
unused goods must be returned promptly. If DTI decides to
keep the goods, payment becomes due.
Payment is due for a service when that service has been
performed (in accordance with the contract). Given that
it is not possible to return a service that has been performed
without DTIs consent, unwanted services, which have not
been ordered by DTI, must be rejected immediately.
E.16.6 Payment in Advance
Payment for goods or services should be made only on completion
of the contract, or in stages for part delivery or completion
if provision for doing so was included in the contract.
However, the amount of each stage payment must equate with
the value of goods or services received at that stage.
Requests for advance payments should be dealt with in accordance
with Accounting Memorandum 2.6.8 - 2.6.12 and Annex 21.1
to Government Accounting chapter 21.
E.16.7 Miscellaneous
For purchases of products made overseas, the contractor
should be made responsible for the payment of import duty
and VAT.
Some suppliers issue documents which appear to be invoices
(giving details of an account number, date and invoiced
amount) which are just invitations to purchase the goods
described. The goods are then despatched after payment has
been received. Matching every invoice with a purchase order
prevents erroneous payments being made against such documents.
E.16.8 Additional Payments
Occasionally it will be appropriate to make an additional payment
to a contractor for goods or services which have a connection
with a particular contract but which are not specifically provided
for in that contract.
Any claim for extra payment should be examined to determine whether
it should be considered as an extra-contractual or ex-gratia payment:
-
- ex-gratia payments are those which are not legally
due but which may be made by way of compensation on the grounds
of hardship or as an indication of goodwill.
- extra-contractual payments are those which are not
legally due under the contract or any amendment, but where it
could nonetheless be argued that there is a legal obligation
on DTI to pay and where it is likely that a contractors claim
will be upheld by the courts.
Additional payments, in particular ex-gratia payments, may have
legal or ethical implications so it is important to take advice
on such claims from FRM2s Procurement Standards Unit or your
Directorates solicitor.
The following table is a guide to the action to be taken in a
variety of potential additional payment situations.
Table -6: Additional Payment Situations
|
Description
|
Category
|
Liability to Pay and Action
|
|
Work done on a cost plus basis costs more than estimate
|
Contractual payment
|
DTI liable to pay
- seek funds from within budget group.
|
|
Contractor miscalculates costs of carrying out contract
|
Ex-gratia payment
|
Do not pay unless
circumstances are exceptional - consult Accounting Memorandum
8.4.2.
|
|
Extra work requested by Department outside the original
specification to complete the job
|
Variation to contract
|
DTI liable to pay
- place written order/ contract with contractor prior to
commencing additional work.
|
|
Extra time required by contractor to complete work
|
Extension to contract
|
DTI not liable to pay
-negotiate variation order.
|
|
Extension of period of a "term" contract.
|
Extension to contract
|
DTI liable to pay
- issue variation order if provision for renewal in the
original specification; otherwise re-tender.
|
|
Increase of quantity to be provided under contract.
|
Variation to contract
|
DTI liable to pay
- issue variation order if value is small; re-tender if
value is great.
|
|
Contractor continues without implied or express approval
or order to provide services. *
|
Ex-gratia payment
|
Do not pay
unless circumstances are exceptional - consult Accounting
Memorandum 8.4.2.
|
|
Additional work required by DTI from same contractor while
on site.
|
New contract
|
Issue new purchase order or contract.
|
|
Payment made in error for goods/services not received and
not refunded.
|
Payment in error
|
Consult Accounting Memorandum 5.4.10.
|
|
DTIs legal advice is to settle claim as there is likelihood
that contractor will succeed in court proceedings.
|
Extra-Contractual payment.
|
DTI accepts liability to
pay - consult your
Directorates solicitor and the Accounting Memorandum 8.4.2.
|
E.17 CONTRACT
MANAGEMENT
E.17.1 Contents
Introduction
General Arrangements
Contract Monitoring
Contract Control
Contract Variations and Extensions (Renewals)
- Contract Variations
- Contract Extensions (Renewals)
- Re-tendering
Completion Reports
Record Keeping
E.17.2 Introduction
This Section of the Manual should be read in conjunction
with CUP Guidance No. 61 on Contract Management.
Contract management is the active monitoring and control
of all aspects of the relationship between the provider
of goods or services and the Department. The primary aim
is to ensure the delivery of a cost effective and reliable
service (or goods) to the agreed price and standard, consistent
with legal requirements and financial propriety.
Contract management arrangements come into effect when
a contract is let. They form a distinct phase within the
procurement cycle and are often carried out by individuals
not involved with tendering or placing the contract However,
it is important to take into account the contract monitoring
and control requirements related to any particular procurement
right from the outset (business requirements stage). In
addition, wherever possible the staff to be responsible
for contract monitoring and control should be identified
at the beginning of the procurement process and should be
involved at the specification stage. This ensures best practice
prior to contract award and reduces the likelihood of problems
arising later.
Contract management is a challenging task. Value for money
will not be obtained if it is neglected. While management
of low value, straightforward contracts may be simple and
routine, at the other end of the scale service contracts
involve issues such as change and uncertainty and the relationships
of the parties in such contracts is also more complex.
In addition, the problems faced with monitoring framework
or call-off arrangements, whilst in many respects similar
to ordinary contracts, might be greater because of the large
number of remote customers. Under such circumstances closer
cooperation with customers will be required in order to
ensure that such monitoring is effective.
E.17.3 General Arrangements
Both parties to the contractual relationship need to establish
contact points at the outset.
For the Department the contact will be the individual appointed
to undertake the task of monitoring. He or she may be given
a formal title such as contract monitoring officer or contract
liaison officer. Whatever the title, ultimate responsibility
for monitoring rests with that individual.
The actual management of the contract is the sole
responsibility of the contractor, not the Departments liaison
officer. The management role is to monitor the contract
and to control the contractors performance so as to ensure
compliance with the provisions of the contract. If performance
falls short it is the liaison officers job to take appropriate
action.
The liaison officer should aim to establish a cooperative,
rather than adversarial, relationship. This is especially
important for those contracts that involve the delivery
of services over a long period.
Ideally, the Department and its contractor should be working
in an atmosphere partnership, as opposed to an arms length
alliance. Best results are obtained through mutual trust,
open contact and pro-active monitoring (as opposed to suspicion,
limited contact and re-active monitoring). The risks involved
in not forming the correct relationship can be considerable,
ranging from increased contract administration and costs
through to the possibility of argument over contract terms
and conditions, which could ultimately involve the courts
(albeit unlikely). Conversely there are major advantages
to be gained by focusing on a shared objective.
E.17.4 Contract Monitoring
Effective contract monitoring requires good two-way communications
between both parties and good management information:
- to satisfy yourself that you have received the goods or service
in a fully satisfactory manner as required under the contract;
- to ensure that the contractor has fully met his obligations
under the contract;
- to identify any opportunities that might exist for improvement
of the contractors performance (which is of course of direct
benefit to the contractor);
- to forecast future trends or needs; and,
- to establish the point or points at which any stage payments
can be made.
The contractor should be required to provide information and
report on his own performance.
The exact monitoring requirements and methodology will depend
on the nature of the contract and the goods or service being provided.
There are nonetheless some standard practices that can apply throughout.
These include:
- monitoring the contractors performance against the specific
targets and levels laid down in the contract (e.g. deliveries
of a set number of items by a given time, or particular milestones
being reached);
- inspection of the completed work (if it is impracticable to
check every item individually e.g. as with bulk stationery
supplies or with a cleaning contract- it is nevertheless always
good practice to inspect at least a random representative number);
- recording complaints received from customers of the service
(to ensure that complaints can be readily dealt with), which
may mean that in cases with a large number of users, such as
call-offs from framework arrangements, bespoke systems have
to be set up to collect and record complaints;
- recording customer satisfaction with the service (different
to recording complaints as it also tries to ascertain positive
- as well as negative - feedback usually via a questionnaire
at the end of a contract or periodically during a contract;
and
- ensuring, for consultancy contracts that there is a system
in place which allows for the project to be formally signed
off on satisfactory completion.
A good complaints and compliments procedure must be capable of:
- tracking individual entries;
- assigning responsibility for investigating reasons for the
complaint or compliment;
- identifying the source of complaint or compliment;
- resolving the problem or building on the success; and,
- responding to the originator.
E.17.5 Contract Control
A key skill for liaison officers is the ability to identify problems
that require corrective action. The type of problems that are
likely to be encountered might include:
- unsatisfactory performance,
- misunderstanding the requirement,
- inadequate channels of communications,
- changes to the contract brought about by unexpected altered
requirements, and,
- contractor insolvency.
Contract control involves actively keeping the contractors performance
to the required standard as required by the contract. Participation
by both parties is needed if this is to be successful to enable
problems to be quickly identified and remedies sought. It is therefore
important that a sound working relationship is established.
Regular contact and monitoring of performance also assists control.
Awareness by the contractor that this is being done can itself
bring to his attention any potential fall-off in his performance.
If monitoring indicates that a contractors performance has deteriorated,
action will need to be taken. The nature of the action will be
dependent upon the level of the under-performance or complaints.
If regular monitoring is effectively carried out problems will
be spotted early and the degree of any disruption from corrective
action will be minimised.
In most cases a discussion of the issue will be all that is required
to secure agreement on remedial action. If this does not work
formal negotiations will have to take place.
Negotiations (whether informal or formal) during the currency
of a contract are a valuable means of resolving problem. A good
client-contractor relationship will help to ease any tension should
the need for formal negotiations arise.
E.17.6 Contract Variations and Extensions
(Renewals)
An important potential outcome of contract monitoring and
control is be the need to change the contract either by
varying the terms and conditions, modifying the requirement,
or extending it because you require the contractor to continue
with the work.
- Contract Variations
Variations to a contract made during its life will not always
be as a result of contract monitoring and control. The Department
may decide during the course of the work that a slight change
to the requirement is needed due to external factors. Contract
monitoring and control arrangements might reveal problems that
need a contract variation in order to regularise a situation,
for example, poor delivery resulting from impracticable timescales.
The Department can at any time request an alteration to the terms
and conditions or make other changes to the nature of the contract.
However, such changes must be agreed with the contractor.
Changes to the contract might affect:
- the specification,
- the quantity of goods,
- delivery time or location, or
- the nature of the service being provided.
It will normally be the role of the contract liaison officer
to ensure that the need for any contract variations are properly
recorded and the contract is suitably amended and subsequently
agreed with the contractor. This may involve liaison with end
users and in some cases the purchaser who let the contract (if
different from the liaison officer). The liaison officer must
also ensure that appropriate financial authority exists or is
obtained if the contract variation involves a change in price.
The variation order must be clearly tied in with the main contract
reference and should be sequentially numbered in order to avoid
any confusion and also to enable a clear audit trail to be established.
Only those individuals with the appropriate delegated authority
have the power to agree to and/or sign a contract variation. Thus
close liaison will be required where pre contract award functions
such as purchasing are separated from monitoring and control.
- Contract Extensions (Renewals)
A contract extension, often termed
a renewal, may arise because of operational difficulties
on the clients side, for example it may be inappropriate
to re-tender and let a contract for a short period because
of an imminent policy change. It may also arise if the
original contract made provision for the term of the
contract to be extended (for example, if the performance
of the contractor was satisfactory or a pilot service
successful). Ideally, a contract should only be renewed
once because technology may improve, the market may
develop or the contract price may become unrealistic.
There is also a risk that "cosy" relationships
may develop with suppliers to the exclusion of new potential
contractors who may have entered the market (see also
Section E.6.6).
If consultancy contracts over-run or need to have their
scope extended take particular care not to drift into
an open-ended sequence of contract extensions.
For contracts subject to EU Directives,
it is important to determine the total contract requirement
at the outset and to include any possible extensions
in the original OJEC Notice. For unforeseen additional
work the EU limits contract extensions to 50% of the
original contract value.
- Re-tendering
It is important to distinguish between a contract extension (or
variation) and a re-tendering exercise. An example of the former
is where a contract needs a short-term extension for a particular
piece of work to be completed or a delivery to be effected as
described above. A re-tendering exercise implies a complete end
or stop to the existing contract to be followed by the
commencement of a new arrangement. The contract may stop due to:
- the end
date being reached;
- a decision to terminate the contract; or
supplier insolvency.
Where one of the criteria above occurs it would be normal for
a new competitive tendering exercise to take place if further
goods or services are still required.
Re-tendering should not normally be used as a threat to improve
a suppliers performance since it will undoubtedly disrupt the
collaborative relationship. Where performance is slipping you
should identify the problem and attempt to find a mutually acceptable
solution, by negotiation if necessary. However, where a solution
cannot be found by negotiation it is inevitable that the contract
will have to be terminated.
If contract monitoring is carried out correctly the need for
re-tendering, whatever the cause, should not come as a surprise.
The specification will have been kept up to date and if procurement
best practice has been followed, information on potential suppliers
will have been accumulated whilst keeping abreast of market.
The re-tendering process should be started well before the end
of the current contract. It is important to ensure that the existing
supplier continues to meet contractual obligations during the
re-tendering period, particularly if he/she is not to be invited
to re-tender.
E.17.7 Completion Reports
It is good practice at the completion of any contract to review
and place on record what went well and what did not, so that lessons
can be learned for the future. This does not always need to be
a major exercise with formal reporting. Depending on the nature
of the procurement it might take the form of a simple note on
the file by the liaison officer.
However, in the case of:
- large procurements,
- projects which were more complex,
- high profile procurements and
- consultancy projects
there should be a more formal post project completion assessment
covering all key aspects of the procurement.
This should include such things as:
- the conduct and outcome of the project,
- the extent to which the expected benefits (deliverables) were
achieved,
- total cost (including full economic cost of in-house staff
engaged on the project).
E.17.8 Record Keeping
Accurate and timely record keeping is essential to provide the
liaison officer with up to date information on the contractors
performance. This can be a manual system, but for complex contracts
a computerised database may be more appropriate.
Records should be maintained of complaints and failures in performance,
and of problems of a recurring nature:
- to act as evidence to support necessary remedial action,
- to monitor performance for payments purposes,
- for possible future use for vendor rating (or reference) purposes,
and,
- to act as an audit trail.
Both parties to a contract should view maintaining records as
mutually beneficial: records are kept primarily to help identify
problems in advance and to set down agreed remedial action by
both parties, not so as to penalise the contractor. Notes of meetings
and important telephone calls should be kept, using some
judgement about whether every single call or short meeting needs be the
subject of a detailed note. Anything that impacts directly on
matters of contract price or contract delivery must be recorded.
E.18 DISPOSALS
E.18.1 Contents
Introduction
Requirements
Responsibility and Authority
Approvals Process
Disposal Board
Information Required
Disposal Routes
- Internal Use.
- Internal Sale
- External Sales
- Tendering
Charitable Sales/Donations
Hazardous Materials
Collection and Completion
Documentation
Receipts
E.18.2 Introduction
The disposal of fixed assets is covered in Government Accounting,
Section 32.
Fixed assets include land and buildings, plant, machinery,
office equipment etc. A fixed asset can be regarded as any
item that is or was intended to provide a service over a
number of years.
This Section of the Manual covers the disposal of goods
and materials. EFM should be consulted on procedures
for the disposal of land and buildings.
E.18.3 Requirements
Any fixed assets (including goods and materials) that are
surplus to requirements should be disposed of as soon as
possible.
Goods that have a resale value should be disposed of to
the highest bidder unless use can be found for them elsewhere
in the department or government service. The disposal method
chosen should be that which best safeguards the taxpayers
interest by securing best value for money. The objective
is to maximise the benefit to the Department, either in
cash terms or by putting the assets to good use in a way
that would benefit either the Department's general aims
or the Government's wider interests. In assessing the economy
of repairs or refurbishment, the value of staff time involved
must be added to the repair cost.
Surplus or obsolete items not considered saleable should
be disposed of in the most economical manner possible.
A note of items disposed of or scrapped must be made against
the relevant entry in the assets register, stock account
or similar record, with sufficient detail to identify the
authority for the action taken. The item being disposed
of or scrapped may exceptionally give rise to a notifiable
loss within the terms of Government Accounting and will
require formal write-off.
E.18.4 Responsibility and Authority
Heads of Agencies and Government Offices who have delegated
authority for purchasing equipment and stores on capital
or current expenditure budgets may also dispose of surplus
or scrap. Other HMUs must refer all surplus office equipment
to IMPE and all surplus furniture to EFM. For advice on
dealing with disposal of other items, contact the Procurement
Standards Unit in FRM2 in the first instance.
E.18.5 Approvals Process
Any officer with delegated authority to incur expenditure may,
subject to the requirement in E.18.3 to refer disposals of office
equipment (including computers) and of office furniture, authorize
disposal of goods whose value (written down book value) does not
exceed 10% of that officers level of delegated authority.
The authorising officer should be satisfied that disposal of
the items is more cost effective than redeploying them and should
ensure that cost effective arrangements are made for managing
the disposal.
Generally speaking an individual should be designated to manage
the disposal (disposal officer). For values over £500 the disposal
officer should be required to work with at least one other officer
to form a Disposal Board.
The Disposal Board (or disposal officer working alone for values
less than £500) should:
- recommend disposal arrangements to the authorising officer
- manage the disposal arrangements once authorised
- seek approval from the authorising officer of its final recommendations
on disposal before confirming the sale.
E.18.6 Disposal Board
For the disposal of commodities, equipment or vehicles where
the sales price is likely to exceed £500, a Disposal Board (DB)
should be convened under the following terms of reference:
- to comprise a minimum of two persons, the disposal officer
and one other,
- to review the documentary submission and, where possible and
economic, view the actual items to be disposed of,
- to set an estimated sales price and decide on the most appropriate
method of disposal, and
- to prepare the tender document and/or the advertisement.
- to maintain clear and concise records.
The DB recommendation should be submitted to the MUFO for approval
and authorisation of disposal.
The disposal officer should issue the invitation to tender or
arrange an advertisement and award the contract, or, where appropriate,
arrange destruction or disposal as scrap.
E.18.7 Information Required
The proposal for disposal must indicate whether the materials
are owned by the DTI. It is possible that material/assets for
disposal may be subject to leasing arrangements, therefore without
terminating the lease and obtaining written agreement to dispose
of the said items, breach of contract or illegal practice may
result.
The officer responsible for disposal will in addition require
the following information:-
- full description (manufacturer/serial nos./supplier codes/
technical data sheets).
- quantity/weight.
- condition.
- value of items - estimated market value and net book value.
- date available.
- approximate age/date of purchase.
- current location/collection point.
- contact for collection.
- former use.
- reason for becoming surplus.
- any other reasons to support disposal.
- proposing officer authorization (signature).
- management approval (where applicable - see E.18.5).
If the disposal relates to computer equipment, the original Purchaser
should be consulted (for HQ Directorates this will usually be
IMPE). The proposing officer must ensure there is no software
or data on the equipment. The disposal officer must also require
the individuals or organisations making an offer for equipment
(whatever the disposal route to indicate in writing their understanding
of software copyright law).
E.18.8 Disposal Routes
There are several methods by which surplus assets and materials
may be disposed of. It is important that the Disposal Officer
judges each disposal activity on its own merit and determines
the most cost effective approach to disposal, using a strategy
appropriate to current market trends.
Example disposal routes are discussed in the following
paragraphs.
- Internal Use.
If a use in other departments/agencies or elsewhere
in DTI can be found, disposal costs can be reduced.
This process should not require significant resources
and will be of greatest benefit for specialist items
where restricted markets reduce market value at the
time of disposal.
- Internal Sale
Internal sale of surplus low value items may be most cost-effective
but staff sales tend to be resource intensive. Safety and legal
requirements necessitate firm control and clear sensible procedures
need to be followed to avoid criticism of unfairness or impropriety.
Once materials have been identified as suitable for sale by this
method, the following steps are recommended:
- individual items of a similar nature should be identified
separately by the allocation of a Lot number;
- the materials should be openly advertised, and
- applications to purchase should be made on form PF90.
The sale should be conducted on principles applied to the standard
procurement tender procedures, this concentrates on the particular
concerns of getting a good return for surplus material.
A sales notice should be issued and drawn to the attention of
all staff via, for example, internal staff notice boards. This
notice should include the following:-
- full description (specification) manufacturers.
- estimated weight.
- condition.
- holding location.
- on-site contact or viewing.
- date available for collection.
- special site requirements.
- conditions of sales (standard PF90 Conditions of Sale should
be utilised).
In considering bids from staff pay particular attention to:-
- whether the officer had been officially associated with the
disposal arrangements,
- whether the officer has been able to obtain special knowledge
about the condition of the item to be sold (which was or would
not be available to other interested prospective purchasers),
and
- whether the transaction would be likely to cause criticism
on low pricing.
- External Sales
Wherever possible, use approved external agents (auctioneers
and organisations providing unrestricted sales to the public and
trade).
One of three routes is specially recommended:
- Select a commercial auctioneer/company based on -
- the best offer from at least three commercial companies
- acceptance of DTI Conditions of Sale as printed on the reverse
of PF90 or GC/SALES 1978 (GC/SALES 1978 should be used unless
the buyers conditions are to apply, in which case you must
record the reasons)
- provision of information along the lines of that required
on PF90,
- Through MOD which operates, a disposal service for government
departments and local authorities either by undertaking the
administration or by accepting goods or vehicles physically
at a number of depots throughout the country. The service includes
dismantling on site as well as at the depots where precious
metals can be recovered and sold at high prices. The MOD charges
a management fee based on the amount of work involved.
- Auctioneers and valuers Martin Spencer-Thomas (MST) previously
arranged disposal of surplus saleable government equipment from
TCS and is now under contract to TBA. Goods for disposal can
be sold on site with the company conducting the auction sale,
collected by MST or delivered to MST's depot in Exmouth. The
area of operation is South of Manchester, elsewhere only by
negotiation with MST. The company will collect and auction for
an all-inclusive commission of between 60% and 80%. The commission
on sales of goods delivered to MST's Exmouth depot and for sales
conducted on DTI premises is between 20% and 50% of the proceeds.
The company will dispose of items that it cannot sell. There
will be no charge for such disposals. The company will accept
for auction almost any saleable commodity. TBA Contract No.
A511825 must be quoted on all orders.
- Tendering
For high value and highly attractive items of a specialist nature
it may be appropriate to offer the goods for tender. However,
this option should be used very selectively as the process tends
to be labour intensive and often fails to produce returns significantly
in excess of the returns achieved by specialist auction groups.
Only use this option where net receipts are expected to be in
excess of advertising, tendering and collection costs etc.
The principles for preparing tender documents and inviting offers
for disposal are the same as those for purchasing. A sound specification
must be prepared to make clear all of the requirements to be tendered.
It is important to make adequate arrangements for tenderers to
view the items for sale. They will be sold as they lie with
such faults and errors of description accepted. it is therefore
up to the tenderers to satisfy themselves as to their condition.
If they purchase on this basis there can be no comeback on the
department because of faults, errors or misstatements.
The tenders should be received, controlled and assessed in accordance
with procurement procedures. However, the following should be
observed:
- the aim is to obtain the highest price,
- if the price offered is below the scrap price the highest
tenderer may be asked to increase his price or the materials
will be disposed of for scrap based on assessed weight,
- tenderers conditions must be fully scrutinised - for example,
firms may quote a price free on vehicle' requiring the Department
to absorb significant costs in providing lifting facilities
or labour - wherever possible DTI conditions of sale as given
on the reverse of PF90 should be applied,
E.18.9 Charitable Sales/Donations
The officer with appropriate delegated
powers (see E.18.5)
should be approached to approve this route.
E.18.10 Hazardous Materials
The rules on the identification, storage and movement of
hazardous materials also apply to their sale and disposal.
Staff responsible for hazardous materials must ensure the
safe custody of such materials up to the point of loading
or destruction. This must be done in compliance with the
provisions of the Health and Safety at Work Act 1974 and
any relevant Regulations and Approved Codes of Practice
made under the Act. The Control of Substances Hazardous
to Health (COSHH) Regulations 1999,) and the Control of
Asbestos at Work (CAW) Regulations 1987 and CAW Amendment
Regulations deal strictly with the control of materials
that pose a risk to health.
No hazardous materials are to be disposed of until the
responsible site or safety officer is satisfied that all
health and safety and environmental requirements have been
observed and, where necessary, advice or instructions have
been passed on to the purchaser.
The disposal of hazardous materials will also need to comply
with the Duty of Care on Waste Management under the Environmental
Protection Act 1990.
E.18.11 Collection and Completion
Collection should be arranged to the satisfaction of the
nominated Disposals Officer to take place as soon as payment
is cleared.
If materials have been sold against an estimated weight,
the purchasers vehicle should be weighed on entering and
leaving the site and weight tickets obtained using a public
weighbridge witnessed by a member of staff.
If several items are sold as a lot the most attractive
item should be released only after the other items have
been loaded.
E.18.12 Documentation
Except for disposals through the MOD depots, all goods
are to be sold "where lying", the buyer (including
staff) being responsible for loading and/or removal from
site.
For all sales, including those to staff, an application
to purchase DTI sale goods (form PF90) must be completed.
All buyers including staff who purchase equipment from the
Department must be issued with an invoice (form DTI 1089M)
which records details of the equipment, the serial number
if appropriate, the date, the price paid and the signature
of the authorising officer. The invoice must be cross-referenced
to the relevant form PF90.
Whatever method of disposal is used, clear records must
be kept providing an auditable trail of the decisions and
actions taken and the authorisations given for the disposal.
E.18.13 Receipts
Payment must be received before goods are released.
All receipts arising from disposals must be credited to Extra
Exchequer Receipts under appropriate ledger headings allocated
by FRM. However, where an item is "traded in" against
new equipment the credit for the part exchange should be discounted
from the purchase price.
Gifts to non-Exchequer bodies must be noted in the Appropriation
Account.
Sales of damaged or obsolete stock that is written off should
be recorded as value for money savings and declared as a part
of the returns for the Treasury's annual reporting exercise.

| index |
|