E.1 ARRANGEMENTS AND RESPONSIBILITIES
E.1.1 Contents
Introduction
Key Stages in Procurement
Responsibilities
Sources of Additional Information
E.1.2 Introduction
The chart below is provided as a graphical representation of the procurement
process and as a simple index to where in this Section of the manual advice
on particular stages is to be found:
Figure -1: Managing the Procurement Process
E 1.3 Key Stages in Procurement
Procurement arrangements in DTI, involving a mixture of centralised and
decentralised procurement, are designed to ensure the benefits of economies
of scale where appropriate without a unified central procurement bureaucracy.
Managers are responsible for ensuring that they meet their procurement
needs by using the procurement route that provides best value for money.
While the precise procurement arrangements will vary according to size
and type, every procurement should involve the following key stages:
- preparing a clear plan for the procurement
- determining the requirement and obtaining the finance;
- identifying sources and choosing the supplier appropriate to the
type and scale of procurement; and
- receiving and managing the goods or services supplied (including
payment and, where appropriate, contract management).
E.1.4 Responsibilities
Responsibility for ensuring these stages are appropriately addressed
rests with everyone in the procurement chain:
- end users need to be clear about their requirements,
- procurement staff need to be appropriately trained to discharge
their procurement responsibilities professionally and effectively
and in accordance with all appropriate legislative and administrative
requirements,
- finance staff need to have appropriate procedures in place
for ensuring expenditure has been properly authorised and that proper
payments are made in timely manner,
- managers need to have robust mechanisms in place for managing
each stage of the procurement, and
- budget holders need to ensure proper arrangements are in
place for approving expenditure and that these arrangements are consistent
with delegated authorities.
The following three tables indicate how responsibilities for various
stages of procurement are normally divided:
Table -1: Roles in the pre-tendering phase
|
ROLES
FUNCTIONS
|
Budget Holder
|
Line Manager
|
End-User
|
Purchasing Staff
|
|
Procurement arrangements
|
|
a
|
|
|
|
Business Case
|
|
|
|
|
|
preparation
|
|
|
a
|
|
|
approval
|
a
|
|
|
|
|
Specification
|
|
|
a
|
|
|
Requisitioning
|
|
|
a
|
|
|
Sourcing
|
|
|
|
a
|
|
Strategy
|
|
|
|
|
|
preparation
|
|
|
a
|
|
|
approval
|
|
a
|
|
|
|
implementation
|
|
|
|
a
|
Table -2: Roles from tendering to ordering
|
ROLES
FUNCTIONS
|
Budget Holder
|
End-User
|
Purchasing Staff
|
Third Party
|
|
Quotations
|
|
|
a
|
|
|
Tendering
|
|
|
|
|
|
ITTs
|
|
|
|
|
|
evaluation
|
|
a
|
a
|
a
|
|
negotiation
|
|
|
a
|
|
|
Debriefing
|
|
|
a
|
|
|
Ordering
|
|
|
|
|
|
preparation of entry form
|
|
a
|
|
|
|
initial authorisation
|
a
|
|
|
|
|
data entry
|
|
|
a
|
|
|
final authorisation
|
a
|
|
|
|
|
issue of purchase order
|
|
|
a
|
|
Table -3: Roles from receipt onwards
|
ROLES
FUNCTIONS
|
Budget Holder
|
Liaison Officer
|
End-User
|
Purchasing Staff
|
Finance Staff
|
|
Certifying receipt
|
|
a
|
a
|
|
|
|
Payment
|
|
|
|
|
|
|
authorisation
|
|
|
|
a
|
|
|
processing
|
|
|
|
|
a
|
|
Contract Management
|
|
a
|
|
|
|
|
Disposals
|
|
|
|
|
|
|
request
|
|
|
a
|
|
|
|
initial authorisation
|
a
|
|
|
|
|
|
implementation
|
|
|
|
a
|
|
|
final authorisation
|
|
|
|
|
a
|
E.1.5 Sources of Additional Information
This Part of the Procurement Manual (Part E) is concerned
with the detailed arrangements for managing the procurement process. While
it endeavours to cover most of the situations likely to be faced by procurement
staff in DTI, it cannot answer every question that could arise. Procurement
Staff should make full use of the expertise available throughout the Department
if they encounter any issues or situations about which they are unsure.
Refer to Part C
of the Manual for general sources of information and advice.
Part-time purchasers and those new to purchasing can
also refer to CUP Guidance No. 39 – Basic Purchasing and Supply – for a
general appreciation and understanding of purchasing and supply work (see Annex 3
for information on CUP guidance notes).
E.2 THE BUSINESS CASE
E.2.1 Contents
Introduction
Coverage of the Business Case
Approval of the Business Case
Special Cases
E.2.2 Introduction
It is a fundamental principle that public money should not be spent unless
the need has been demonstrated. The business case is a statement defining
in a rational manner the need for the purchase and is the first stage
in the procurement process. Approval of a business case must always be
sought before proceeding further with the procurement.
The end user or customer should be responsible for writing the business
case unless they do not have the detailed knowledge to make a case, for
example when procuring IT equipment. The appropriate procurement specialist
should then draw up the business case in consultation with the end user
or customer.
In a number of parts of the Department formal structures are in place
to ensure procurement proposals are adequately researched and properly
documented and are processed through to approval of funding. This Chapter
of the Manual sets out the general principles which should underpin such
standing arrangements and which should be applied wherever more ad hoc
arrangements are needed.
Special procedures apply to the approval of proposals
for consultancy contracts (see Section E.2.5a).and
to the procurement of legal advice (see Section E.2.5b).
E.2.3 Coverage of the Business Case
The amount of detail included in the business case should be proportional
to the value and complexity of the proposed purchase. A full case paper
would be expected for a high value complex piece of work, whereas a short
minute might suffice for a relatively cheap off-the-shelf item. The amount
of effort in producing the case should be commensurate with the value
of the intended purchase.
A good business case should cover:
- Summary. This should highlight the main features, detailed
below, of the business case. For relatively small purchases the summary
itself will be sufficient.
- Purpose of the goods, services or works. This is the essence
of the case and should set out in clear terms how the intended purchase
is to assist the Management Unit in achieving its aims and objectives.
- Benefits that will be derived. Wherever possible, identify
benefits in terms of financial savings and non-financial savings expected
from the intended purchase. This should be a key feature where expenditure
is significant. Benefits should be quantified and measurable so that
the success of the procurement can be evaluated. Examples of benefits
include the expected savings that will be generated as a result of
an organisational study, the amount of skill transfer as a result
of a training event, the size of the audience to be reached in a promotional
campaign or the value likely to be added to policy advice. Include
efficiency and effectiveness benefits where relevant. For large or
complex procurements formal investment appraisal techniques should
be used to ensure that the best value for money options are being
proposed. Further information on investment appraisal can be found
in the "Green Book": "Economic Appraisal in Central
Government - A Technical Guide for Government Departments" prepared
by HM Treasury and published by HMSO, 1991 (ISBN 0-11-560034-5). In
the case of consultancy proposals make clear what the deliverables
are expected to be.
-
Framework
arrangements.
Whether research has taken place into whether there is an
existing Framework Arrangement or Agreement for these goods
or services and, if there is, why it is not appropriate to
use this Framework Arrangement or Agreement. DTI’s range of
Framework Arrangements and Agreements can be found at Annex
1.
- Total costs. The total estimated costs,
including those associated with equipment maintenance, disposal and
contract management, should be set out. Where applicable, the VAT
element must be included in the cost make-up. Identify where costs
fall to different budgets or ledger headings (for example running
costs for management and programme costs for the project). Take into
account the requirements of EU Public Procurement Directives and the
WTO(GATT) Government Procurement Agreement (see Chapter
E.8
on EU Directives).
- Related action. Indicate plans for implementing follow-on
or related actions associated with the procurement including:
- any requirement for consultancy advice or customer surveys to help
define the specification or for training where software is being bought;
- the timing of organisational or policy changes following a review;
or
- arrangements for an evaluation at the end of the procurement exercise.
Where procurement (e.g. of contracted-out services), follows an appraisal
of options, such as market testing, that prior appraisal project should
have identified they key issues that would form a business case. It may
still, nevertheless, be necessary to submit the results of that prior
appraisal exercise, together with detailed postings and plans for the
conduct and management of the procurement, for formal approval (and authorisation
of funds) prior to initiating further procurement action.
E.2.4 Approval of the Business Case
The customer or purchaser placing the order must obtain approval for
the business case from a manager with both the appropriate level of delegated
financial powers to authorise expenditure and an allocated budget for
the goods, services or works.
Maintain a clear separation of duties as a control over any potential
impropriety. Ideally, the person who authorises expenditure from a budget
should not also be responsible for placing the order (making the commitment).
The person approving the business case will need to ensure that it is
persuasive in all respects and in particular that:
- the purchase is necessary to assist the Management Unit in its work
and is not merely desirable;
- the procurement provides value for money;
- a budget exists to cover the cost of the proposed purchase including
any VAT;
- due attention has been paid to contract monitoring and control,
particularly in the case of large service contracts;
- private sector contributions have been sought where the work will
benefit industry, and
- arrangements have been made for reviewing the project on completion
(wherever appropriate).
If necessary, obtain expert opinion before approving business cases.
Approval should be given in writing. Where a centre of expertise is requisitioned
to carry out some or all of the subsequent purchasing functions Form PF20
should be used to confirm that such a business case has been presented
and approved.
Formal business cases can be dispensed with for routine,
low value (i.e. less than £500) purchases. Separation of duties should
still be maintained (see Section B.1.4)
and the person placing the order should seek approval for the purchase.
E.2.5 Special Cases
- Consultancy Contracts
Contracts for external consultancy exceeding £10,000 in value require
prior approval by Ministers. For contracts whose value is between
£10,000 and £40,000 seek approval from the relevant junior Minister.
For contracts whose value exceeds £40,000 seek approval from the Secretary
of State.
External consultancy is defined as that which is concerned with investigating
problems, providing analysis or assisting with the development of
new systems, new structures or new capabilities within the
organisation.
It covers all types of management consultancy, including reviews or
evaluations of activities, functions and programmes, work on privatisation
and contracting out and feasibility and strategy studies carried out
by IT specialists and consulting engineers to enable management (rather
than technical) decisions to be made.
- Legal Advice
Legal advice is available from the Legal Services Directorate but Management
Units have the option of obtaining legal advice directly from outside lawyers.
However, advice relating to "core governmental work" can be obtained
only from in-house lawyers.
"Core governmental work" has been defined by the Attorney General
and includes (but is not confined to):
- work with national security or other especially sensitive implications;
- work relating to major policy or constitutional issues;
- Government to Government and other international non-commercial work;
- work affecting the long-term interests of more than one Department;
- work where Cabinet Office coordination is necessary.
Management Units should consult the Legal Services Directorate at an early
stage before procuring legal advice externally and must take the Solicitor’s
views into account. Where it appears that the legal advice being sought may
relate to "core governmental work", proposals to procure it externally
must be put to the Solicitor in writing, allowing at least 5 days for the Solicitor
to give a view.
Where the legal advice sought does not relate to "core governmental work,
the Solicitor can offer a view on conflict of interest issues or on the relative
merits of particular organisations and may lay down requirements in particular
cases (e.g. if the legal advice sought is close to "core governmental work")
for certain aspects of the legal advice given to be referred to him.
Whenever the proposal to procure legal advice externally does not relate to
core work the Management Unit will be responsible for setting up the contract,
ensuring best value for money and managing the contract. The Legal Services
Directorate will, where relevant, offer guidance on appropriate outside organisations
and on terms of contract. The Legal Services Directorate may undertake, on an
ad hoc basis, quality assurance monitoring only of work done by outside lawyers.
The Directorate will not, routinely, provide a second opinion on legal advice
obtained. If they do so, it will be charged for.
The Solicitor must be consulted on any proposals to go to Counsel and on any
proposals to consult the Law Officers.
Consult the Legal Services Directorate if you are unsure about the application
of this guidance.