This snapshot, taken on 21/12/2003, shows web content selected for preservation by The National Archives. External links, forms and search boxes may not work in archived websites.
Department of Trade and Industry
TEXT ONLY | SITE INDEX | FEEDBACK | CONTACT GO
GO GO GO

 

DEPARTMENT OF TRADE AND INDUSTRY

UK COAL OPERATING AID SCHEME

IMPORT PARITY PRICE PANEL - RESPONSE TO CONSULTATION


1. INTRODUCTION

The Import Parity Price Panel (IPP Panel) has been established to advise the Secretary of State on certain contracts submitted as part of an application for subsidy under the UK Coal Operating Aid Scheme. The Panel will advise on what the price would be (the IPP) of imported coal of equivalent quality purchased under terms comparable to those in the UK coal contracts.

The Panel issued a Consultation Document on 15 December 2000, which set out the general methodology it intended to use to set IPPs, and sought views on a number of specific issues. This Paper can be found at www.dti.gov.uk/support/coal.htm. Responses were received from fifteen parties, listed at Annex A. In addition the Panel has held meetings with the principal trade associations representing UK coal producers, and with a number of other parties with expertise in specific areas relating to the import of coal.

This paper sets out the main points raised in the consultation process, and the Panel's conclusions on these issues. On one issue, highlighted in Section 2, the Panel is inviting further comments. As previously indicated, the Panel will undertake a detailed examination of all contracts submitted to it, and the circumstances surrounding their negotiation, including inviting representations from the applicant for subsidy and usually also the customer for the coal.

The Panel's Terms of Reference were set out in the Consultation Document (at Appendix A). Some of the comments received would have required to Panel to go beyond its Terms of Reference. We have been conscious throughout of the need to comply as closely as possible with the spirit of these Terms.

This paper covers the topics in the same order as in the Consultation Document. Paragraph references are to those in the original Document.


2. IMPORT PARITY PRICE PRINCIPLES

General

Many respondents to the Consultation Paper have raised issues in relation to the phrase "contracts to secure coal of similar quality and on similar terms" in the Panel's Terms of Reference. The Panel is also aware that the nature of many of the contracts which it will be required to examine is such that some of the methodology set out in the Consultation Paper may not be appropriate.

In particular, this applies to specialised qualities including anthracite and coals with unusual characteristics such as low volatile South Wales steam coals. In examining contracts for the supply of such coals, the Panel will be undertaking specific market research amongst traders and users in order to derive an IPP which takes into account the specialised qualities involved. In certain cases, the Panel may come to the conclusion that there is no commercially credible non-UK source of supply. If that is the case, then it will form part of the Panel's advice to the Secretary of State.

In relation to high specification, low ash industrial coals supplied in small quantities to small businesses and public authorities, the Panel has identified a number of sources of such coals based on plants processing imported coals at various locations in the UK. When examining a particular contract, the Panel will undertake specific research into such sources to establish an IPP for an equivalent imported coal delivered on the same terms.

In some cases, a UK contract may be for general purpose steam coal that is available from non-UK sources but the terms of the contract (e.g. very low rates of delivery) are such that they are not normally applicable to contracts for the purchase of imported coal. In these cases, it will be necessary for the Panel to examine what the alternatives were, or might have been. A possible import alternative would have been the supply of residual power station fuel from a plant processing imported coal primarily to produce high value products for premium housecoal or industrial markets. Following this research, the Panel will derive an IPP on similar contract terms. In extreme cases, the Panel may conclude that there is no commercially credible import alternative. Such a conclusion will then form part of the Panel's advice to the Secretary of State.

Availability of Longer Term Import Contracts (paras 2.3 to 2.4)

Two respondents suggested that longer term import contracts (i.e. for more than one year) could be available on fixed terms other than at prices linked to an index of world market prices. Other respondents said that import contracts were not available on fixed terms and that it was not possible to compare long term UK contracts at these prices with one year import contracts. On the other hand, one respondent said that comparison with one year import contracts, revised each year, was the only true comparison. If evidence is provided to the Panel when it considers a long term UK contract that imports were available for the same duration at fixed prices, the Panel will take this into account in determining the IPP. Such evidence must be documented, for example a quote in response to a tender, or a firm offer to supply.

If no such evidence is presented, the question then arises as to how a long term IPP might be derived. The Panel has been advised that certain traders would quote a fixed price for a long term contract if asked to do so. It is clear, however, that such a price would be likely to be different from the then current international price as it would anticipate future price movements. When prices are low, therefore, it would be significantly above the current market and when prices are high, it would be lower. Given competitive pressures, it seems unlikely that a customer would be prepared to pay significantly above the prevailing market price for imported coal on the assumption that it would rise much higher in future years. Similarly, when prices are high, it seems unlikely that an overseas producer would be prepared to accept a price well below the prevailing international market price on the assumption that prices will later fall significantly. For these reasons, the only long term contracts that are likely to be concluded are at prices linked to an index of world market prices. This is comparable in economic terms to a long term price which is fixed in real terms.

The Panel is therefore minded to conclude, in the absence of firm evidence that prices for more than one year fixed in nominal terms (or linked to the UK RPI) would have been available for contracts from non-UK sources, that the IPP for a long term UK contract should change for each year of the contract in line with the movement in international prices. In such cases, the IPP for the first year under a long term UK contract would be derived from the delivered price for international coal at the time the contract was finalised, and for the second and subsequent years of supply, the IPP would change in line with international prices.

The Panel recognises that this is not the only approach to this issue which merits consideration. In particular, it can be argued that the IPPs determined at the time that long-term UK contracts were finalised should remain for the full length of such contracts (subject to indexation equivalent to that in the UK contracts) on the grounds that the negotiated prices will anticipate future movements (both up and down) in the international price and will therefore reflect the anticipated average of the international price over the duration of the contracts.

This matter was raised in general terms in the earlier Consultation, but because of its importance and in the light of the more specific proposals now outlined above, the Panel wishes to provide the opportunity for further comment before reaching a conclusion. The Panel would welcome further views from interested parties on the methodology that should be adopted for the determination of IPPs for long-term UK contracts in cases where specific evidence of longer-term import quotations is not available. Consideration of this issue is unlikely to delay the Panel's deliberations and advice on IPPs for contracts relating to first tranche subsidy applications.

Options (para 2.5)

There was a variety of responses to the Panel's request for views as to how options in UK contracts might be valued in comparison with international contracts. Views ranged from any attempt at quantifying the value of an option as not being meaningful to a statement that options can always be valued by the use of appropriate econometric techniques. The Panel is aware that in UK contracts options are usually at the buyer's call but that the producer is not always obligated to supply in full. From the buyer's perspective, therefore, an option may have some value.

The Panel has concluded that longer term options have no quantifiable value at the time they are negotiated given the volatility in world prices. Depending on their terms, short term options can be valued by comparing them with the alternatives that were perceived as being available at the time of their negotiation. In considering a UK contract containing an option, the Panel will assess its value taking into account the terms of the option and, in particular, the extent to which the producer is obligated to supply.

Coal Price Indices (Paragraphs 2.7 to 2.18)

The Panel received ten responses to this section of the consultation. Some respondents thought the MCIS marker price was the most appropriate whereas one considered the API#2 index to be the best indicator of the current international coal price, and one thought that a basket of indices should be used. Some made the point that small producers had to accept an RPI-x formula imposed by large buyers, irrespective of the cost of imported coal. Other respondents considered that the UK price had been determined by large contracts, and their impact in foreclosing the market to other suppliers, not by imported coal prices as reported in various indices.

One respondent made the point that existing indices were not in fact true indices, as they are based upon the opinions obtained from market players and not on actual contract tonnages, terms and pricing. The involvement of trading entities may cause index distortion, and possible manipulation.

A further respondent made the point that whilst coal price indices are a good guide to the direction the market is moving, they are not such a good guide to absolute prices, and the Panel should base its judgements on actual quotations for supply.

Producers who supply niche markets for particular quality coals considered that there was no equivalent imported price quoted by any index for their specialised products. Published indices for steam coals are only appropriate for high volatile coals and an indexation approach would be inappropriate for anthracite and low-volatile coals produced in South Wales. The Panel agrees and will determine the IPP for such products following specific market research. Such an approach was favoured by a number of respondents.

The ideal situation would be for purchasers of UK coal under contracts relating to subsidy applications to disclose what import alternatives were available at the time of negotiating and concluding the UK contract, and the price that would have had to be paid for them. The Panel will require firm evidence of actual quotations available at that time. In the absence of firm quotations the Panel considers that the use of indices set out in the Consultation Paper will apply. Following further research and analysis of the basis of the indices available, the Panel has decided that the MCIS Marker Price
is the most representative of current prices and therefore the most appropriate starting point from which to assess the IPP for coals other than specialist quality coals. Accordingly where no firm evidence of a price for an import alternative is made available, the Panel will adopt the MCIS Index for the appropriate period when compiling the IPP.

Period over which to apply an index (para 2.19)

The Panel had suggested that where an index is to be used as the starting point to derive an IPP, it should be the average of that index over the three-month period immediately prior to the finalisation of the UK contract. By finalisation was meant conclusion of the principal terms, whether by way of a full contract, Heads of Terms, or exchange of letters, whichever was the earliest. Two respondents felt that three months was too long a period, and that particularly at a time of price volatility, only the final month before finalisation should be considered. Alternative views were expressed that three months was too short a period, as price was often firmed up early in the negotiations. Others agreed that three months was reasonable.

The Panel will seek evidence as to the time at which the price of the UK contract was established, but in the absence of specific evidence, reaffirms that three months is the appropriate period to use.

Exchange Rates (paras 2.20 to 2.21)

The Panel received general support for its proposals on exchange rates. One respondent said that the forward exchange rate should be the average for the period of the contract rather than the mid point and another pointed out that forward rates, which are freely quoted only for a year ahead, are not available for the duration of some contracts. It was also pointed out that the forward rate should not be used if it was falling steeply at the time the contract was being negotiated. The Panel agrees with these responses and will use the average forward rate. For contracts of more than one year's duration, the twelve month forward rate will be used. If the forward rate is falling at the time of negotiation, the Panel will consider the rate of fall and whether it was sustained over the period of negotiation, and decide whether the spot rate should be used.

One respondent said that the forward rate to be used should be that for the month of finalisation of the UK contract rather than the average for the three months up to finalisation. However, in comparing UK contracts with contracts for international supplies, UK deliveries can commence almost immediately, but it will be some weeks before imports start to be delivered. The Panel, therefore, remains of the view that an average for the three months prior to finalisation is appropriate.

The Panel was also reminded that in some cases imports are quoted in sterling terms (e.g. anthracite) and the exchange rate is not relevant.


3. PRICE ADJUSTMENTS

The Terms of Reference require the Panel to take account of coal quality, and to set the IPP on the basis of coal of equal value in use to the purchaser.

Coal producers made a general point that the cumulative impact of quality parameters needed consideration, as well as the individual components. Certain UK coals suffer from disadvantages against imported coals by being on the high side in sulphur, chlorine, ash and moisture; and are closer to the borderline of acceptability in other respects such as ash characteristics and consistency. While each individual parameter can be within agreed tolerances, the cumulative impact of these being at the less desirable end of the scale can adversely affect the price. The Panel recognises that this may be the case, and will take into account evidence to this effect presented in relation to individual contracts.

Calorific value, ash and moisture (paras 3.5 - 3.7)

It was pointed out that some coals, such as washed anthracites, are sold on the basis of price per tonne, and that precise calorific value, provided it is within the bounds of normal variation, does not matter. Moisture, on the other hand, is significant, as are certain other properties such as sizing and surface characteristics.

One respondent indicated that individual power stations had expressed concern over high ash or moisture content of certain coals, which could affect the price. Another noted that the ash levels in imported power station coals covered a wider range than had been indicated in the Consultation Document, and that some higher ash imported coals had been bought at discounted prices. One coal consumer emphasised the importance of the quality and quantity of ash at individual power stations, particularly in relation to sales of ash and costs of ash disposal.

The Panel notes these points, and will reflect evidence brought to its attention during the determination of IPPs.

Sulphur (paras 3.8 - 3.10)

A variety of views was expressed. One respondent said there should be no penalty for high sulphur coal: if a generator was freely buying higher sulphur UK coal, it must be assumed that it could achieve its planned generation within its sulphur limits using that coal. Another emphasised the disadvantages of lower sulphur coal in terms of precipitator performance and other adverse effects on plant. One reply said that very low sulphur coals could have distinct advantages for generators at non-FGD stations. Coal producers drew attention to the pricing pressures they had experienced on high sulphur coals, particularly where it was necessary to sell coal through a third party to blend down the sulphur level.

The Panel believes that there is a price penalty for coals with a sulphur content significantly above international levels. Where possible, a market-based approach will be adopted through an assessment of the international price for comparable high sulphur coals, although at present very little is being bought in Europe. For coal sold to an FGD station, the Panel will seek information on the additional costs of using high sulphur coal. Where it is necessary for a producer to sell coal for blending through a third party, the additional costs will be taken into account in setting the IPP.

Chlorine (paras 3.11 - 3.12)

Two respondents felt that any penalty for high chlorine should be applicable over 0.4% rather than 0.5%. The Panel agrees.

Differential Loss of Heat Content (para 3.17)

A number of respondents commented on this matter, but only one felt that it was a real issue, saying that there could on occasions be a material heat loss between loading port and delivery to power stations, depending on the particular circumstances. One respondent pointed out that heat loss also applies to UK coals. In view of the limited information presented, the Panel does not propose to take this factor into account.

Premium for UK coals (para 3.20)

A range of views was expressed, from those saying that there was no longer a premium on UK coal, to those who felt that there was still such a premium. One view was that there was a premium at times when international prices were low, but that at times of high prices, UK coals sold at a discount to the prevailing international price. The Panel continues to believe that there are some largely unquantifiable advantages in buying UK coals which may be reflected in prices at times of market weakness, but that in the power station market the increasing diversity of ownership has significantly reduced the scope for a premium. The Panel will not as a general rule take this factor into account.

Impact on world market prices (para 3.21)

Only one respondent commented on this issue, disagreeing with the Panel's view that the subsidy would have only a small effect on world prices and suggesting that the effect should be modelled once the extent of the tonnage supported in each year is known. The Panel accepts that, particularly at times of market tightness, there might be a temporary effect on world prices if there were to be significant additional demand. Over time, the impact would reduce as more production is made available. The Panel will consider whether this factor should be taken into account particularly for contracts signed since the market strengthened during the year 2000, and if so, the techniques that may be available to model the effect. The modelling exercise could be complex, involving a large number of variables, and would have to take account also of the extent to which contracts may have been awarded to other UK producers as opposed to imports.


4. SHIPPING AND PORT ISSUES

Responses to this section of the Consultation Document concentrated on the issue of port capacity constraints. Comments ranged from support for allocation on a first come, first served basis to ignoring the port capacity issue for all but the largest contracts. One view was that the allocation should be to the nearest port at which capacity was available at the time a contract was let. Respondents made the point that port capacity and choices may be limited by "take or pay" type arrangements.

For specialist quality coals and anthracite, port capacity was not an issue, as these products would be imported in small quantities through a wide choice of import terminals.

The Panel acknowledges that some port capacity is unavailable or limited by previous contracts, and that there may be further limitations because of "take-or-pay" arrangements between ports and importing companies. The Panel does not agree to allocation of capacity on a first come, first served basis as that method would not recognise that some UK coal contracts would not have been replaced by imports but by other UK producers. Equally the Panel does not agree that it should always be the nearest port at which capacity is available, because this ignores the fact that earlier contracts may have used up some of the capacity, had the subsidy not been available.

For small contracts the Panel believes that there will always be capacity available through low cost import routes. There will always be a degree of flexibility at the margin at large ports and capacity at ports limited to dealing with small cargoes will be available. For larger contracts, the Panel recognises that the lowest cost import route may not be available in full and subsequent large contracts may therefore need to be allocated to higher cost routes. In coming to their judgement on this issue, the Panel will take into account the extent to which contracts may have been awarded to UK producers.

In its Terms of Reference, the Panel is explicitly required to take account of infrastructure limitations. In particular where transport infrastructure would be insufficient for the full set of contracts under consideration, a higher price must be estimated to take account of the costs which would be incurred in expanding capacity or using alternative transport.

In order to supplement the Panel's knowledge on port issues, external research was commissioned from the research department of an internationally recognised ship brokerage company, following a competitive tendering process. This complemented the Panel's knowledge of port infrastructure limitations, capacity and costs of use. The Panel will also keep under review the available capacity at UK ports where Corus Group currently import coal and iron ore, as the future plans for this company are developed.

The report also provided data on the differential in CIF (Carriage, Insurance and Freight) rates between shipment costs to Rotterdam and the main UK ports of entry for imported coal. From the information provided the Panel are developing a methodology that is applicable in general terms for converting the MCIS marker price to a CIF price at UK ports for different sizes of vessel.


5. INLAND TRANSPORT

The majority of respondents commented briefly on this issue. In the main, the Panel's proposals were agreed, and the points made were ones of detail.

Rail transport

One response argued that long-distance rail flows for imports may be subsidised, that track upgrades to handle increased import flows are not fully paid for by such imports, and that freight facilities grants distort infrastructure pricing.

The introduction of competition into the rail freight market was noted by one party, with the expectation that this would lead to downward pressure on rates.

The Panel has had helpful discussions with EWS, Freightliner Heavyhaul and Railtrack. We are well advanced in establishing a matrix showing the differentials in transport costs between conveying imported and UK coal to the principal customers. We have been made aware that the Rail Regulator has been consulting on a change in the way in which track access charges are levied on the operating companies, and that such a change may be introduced during this year. This could well have an effect on the rates levied by the operating companies on their customers, and alter the differentials between long and short distance routes. The Panel will keep rail rate differentials under review.

The Panel has also consulted the three companies mentioned above on rail capacity issues affecting movements from ports, and has formed a realistic view of the location and extent of infrastructure and resource capacity limitations. Where appropriate, these will be taken into account in assessing IPPs. One respondent felt that in some cases the availability of rail paths is more likely to be the cause of constraints than port capacity, and that a "first come, first served" approach to allocation of rail capacity should be adopted. The Panel agrees that, for example, in considering movements from Scotland to England, rail capacity is a greater constraint than port capacity. The Panel will also keep under review the impact that changes in the operations of Corus Group may have on the availability of rail capacity from certain ports.


Road transport

For road transport, some coal producers did not feel that the use of typical RHA rates, in the absence of specific information on road rates, would be acceptable. They felt that comparison with rates for similar journeys involving coal transport, and in similar types of vehicle, would be more robust. The Panel agrees provided that sufficiently authoritative information can be obtained.

One producer said that not all power stations were willing to accept deliveries by road, and that the non-rail connected producer may have to go through an intermediary's railhead at extra cost. Where this is the case, the extra cost will be taken into account by the Panel in assessing the IPP. It was also said that the cost of road transport over longer distances limited coal sales options for non-rail connected producers.


6. CONCLUSIONS

In the Consultation Document the Panel had suggested that three factors would be most significant in the determination of an IPP:

• The estimation of a dollar price of imported coal in hypothetical contracts that the purchaser would have purchased had he not signed a contract for UK coal

• The selection of the port or ports through which such hypothetical imports would have been shipped, and the resultant costs

• The estimation of transport costs between the ports and points of consumption, and (where this not explicit) between the UK production or loading points and the points of consumption.

One response commented on this, saying that the first factor should be amended to read "The estimation of a dollar price, taking into account duration, quality and quantity, of imported coal…". This is in line with the Panel's own proposed approach.

Views are invited on the issue highlighted in Section 2, namely the most appropriate methodology for setting IPPs for long-term UK contracts. Comments should be sent to:

Arantxa Fernandez
Department of Trade and Industry
EPTAC 5C - Coal Unit
295 - 1, Victoria Street
London, SW1H 0ET
E-mail: arantxa.fernandez@dti.gsi.gov.uk

Annex A

RESPONSES TO CONSULTATION DOCUMENT

1. AES Drax Power
2. BACM-TEAM, The British Association of Colliery Management
3. Betws Anthracite
4. CLG Energy Consultants
5. Coalpro-The Confederation of UK Coal Producers
6. Edison Mission Energy
7. Edwards Energy
8. FIM-Federation of Independent Mines
9. Hay Royds Colliery
10. Hugh M Lee
11. Moorside Mining
12. Naloo-The National Association of Licensed Opencast Operators
13. RJB Mining
14. Scottish Coal
15. Scottish Power

 

Back to coal main page

Last updated 8 February 2001

Back to Top

Back | index | Forward