Breaking News
Feature
Better information for your journey
The National Traffic Control Centre collects real-time information on road conditions.
Quick Links
How We Manage Our Roads
In this section you can find out more about how we manage and maintain these roads and plan for the future
The Project Control Framework
This framework sets out how we, together with the Department for Transport, manage and deliver major road improvement projects.
Traffic news on your desktop
Helpful ways to access the latest traffic information when you need it.
A5 Europark
A5 Europark
The Project
Improvements to the A5 Watling Street to provide a priority junction for access to the Europark site and closure of the current access junction.
The works involved:
- Construction of a right turn lane into the site (southbound)
- Closure of the existing central reserve gap and creation of a new gap
- Construction of merge and diverge tapers on the northbound carriageway
- Renewal of road markings and studs
- Resetting of ironworks and manhole covers
- Installation of new concrete kerbs and traffic signs
The project started at the end of April 2010 and completed in August 2010.