This snapshot taken on //+, shows web content selected for preservation by The National Archives. External links, forms and search boxes may not work in archived websites.

Latest traffic information

Breadcrumb Navigation

You are here:

  1. »
  2. Home »
  3. Road Projects »
  4. Road Projects »
  5. Area 3 »
  6. Road Project

Website Navigation

Useful Links

Quick Links

Map Based Road Projects Finder - Feedback

We are currently piloting a new map based tool to help you find road projects. Please let us know what you think

How We Manage Our Roads

In this section you can find out more about how we manage and maintain these roads and plan for the future

The Project Control Framework

This framework sets out how we, together with the Department for Transport, manage and deliver major road improvement projects.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

M3 J3-2 Hard Shoulder Strengthening

M3 J3-2 Hard Shoulder Strengthening

Status
Completed
Located in
Area 3Map of the Agency's Operational Areas
Scheme type
OtherRoad Schemes Managed by the Highways Agency

The Project

The major maintenance scheme on the M3 between junction 3 and 2 is now complete. Work was carried out between Kitsmead Lane overbridge and the junction 3 overbridge in order to replace and strengthen sections of the existing hard shoulder. Associated drainage works were carried out at the same time and a new safety barrier was installed.

Work on the 3.9km stretch of motorway began in December 2009 and was completed in July 2010.