This snapshot taken on 08/09/2010, shows web content selected for preservation by The National Archives. External links, forms and search boxes may not work in archived websites.

Latest traffic information

Breadcrumb Navigation

You are here:

  1. »
  2. Home »
  3. Road Projects »
  4. Area 1 »
  5. Road Project

Website Navigation

Useful Links

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

How We Manage Our Roads

In this section you can find out more about how we manage and maintain these roads and plan for the future

The Project Control Framework

This framework sets out how we, together with the Department for Transport, manage and deliver major road improvement projects.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

A30 Alphington Underbridge Repairs

A30 Alphington Underbridge Repairs

Status
Completed
Located in
Area 1Map of the Agency's Operational Areas
Scheme type
OtherRoad Schemes Managed by the Highways Agency

The Project

The concrete beneath the two bridges which carry the A30 over the Alphington Roundabout required some repairs and general maintenance. The concrete was thoroughly cleaned off and repaired using specialist materials.

We also took the opportunity to construct a maintenance layby and footpath in the centre of the roundabout, so that our maintenance teams can park their vehicles safely and access equipment beside the trunk road.

The works began in July and were completed by the end of August 2009