This snapshot taken on 06/06/2011, shows web content selected for preservation by The National Archives. External links, forms and search boxes may not work in archived websites.

Latest traffic information

Breadcrumb Navigation

You are here:

  1. »
  2. Home »
  3. Road Projects »
  4. Road Projects »
  5. Area 3 »
  6. Road Project

Website Navigation

Useful Links

Quick Links

Map Based Road Projects Finder - Feedback

We are currently piloting a new map based tool to help you find road projects. Please let us know what you think

How We Manage Our Roads

In this section you can find out more about how we manage and maintain these roads and plan for the future

The Project Control Framework

This framework sets out how we, together with the Department for Transport, manage and deliver major road improvement projects.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

M3 J3-4 Drainage Phase 3

M3 J3-4 Drainage Phase 3

Status
Completed
Located in
Area 3Map of the Agency's Operational Areas
Scheme type
OtherRoad Schemes Managed by the Highways Agency

The Project

The third phase of improvements to the drainage system on the M3 between junctions 3 and 4 in Surrey is now complete.

The scheme involved replacing the existing verge drainage on the southbound carriageway with a new and more effective drainage system, ensuring the carriageway remains safe and reliable for drivers.

Work on the 1km (0.6m) stretch of motorway began on 22 June 2009 and was completed in late September.