Feature
Better information for your journey
The National Traffic Control Centre collects real-time information on road conditions.
Quick Links
How We Manage Our Roads
In this section you can find out more about how we manage and maintain these roads and plan for the future
The Project Control Framework
On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.
Traffic news on your desktop
Helpful ways to access the latest traffic information when you need it.
A49 Onibury Resurfacing
A49 Onibury Resurfacing
The Project
Where
The scheme is located on the A49 between Onibury level crossing and the village of Bromfield
When
The works started on the 4th of August 2009 and was completed on 19 November 2009.
What did we do?
The re-surfacing works involved overlaying the existing carriageway with 200mm of new surfacing materials together with associated kerbing work and re-setting of manholes and gulleys.
Why did we need to do this work?
The existing carriageway was showing signs of failure. It has required numerous areas of patching to keep it in a safe and serviceable condition for the road user.