Feature
Better information for your journey
The National Traffic Control Centre collects real-time information on road conditions.
Quick Links
How We Manage Our Roads
In this section you can find out more about how we manage and maintain these roads and plan for the future
The Project Control Framework
This framework sets out how we, together with the Department for Transport, manage and deliver major road improvement projects.
Traffic news on your desktop
Helpful ways to access the latest traffic information when you need it.
M6 Junction 14 to 15 Northbound and Southbound Resurfacing
M6 Junction 14 to 15 Northbound and Southbound Resurfacing
The Project
This scheme was a resurfacing project extending over 1km of dual 3 lane motorway and hardshoulder situated between Junctions 14 to 15 of the M6 motorway through Staffordshire. The road surface was worn out and needed replacing. The project provides a new quieter and safer surface and will minimise future maintenance disruptions.
The work started on the 12th January 2009 and were substantially completed as of 5th March 2009.
The scheme comprised of:
- Pavement reinstatement;
- Upgrade of verge road restraint system;
- Repairs to ironwork;
- Replacement of damaged asphalt kerbs;
- Replacement of defective drainage pipes; and
- Reinstatement of road markings.