A66 Viewley Hill Farm to Elton House
A66 Viewley Hill Farm to Elton House
The Project
The scheme involved the renewal of the carriageway and patching in lanes 1 and 2.
This scheme was part of a contract of works, which included the A66 Elton to Preston Farm and A66 Yarm Road to Woodcroft schemes, which started on 20th October and was completed on 18th December.
The scheme cost is an estimated £1.86m and the overall works costs are expected to be £2.528m.