This snapshot taken on 10/11/2010, shows web content selected for preservation by The National Archives. External links, forms and search boxes may not work in archived websites.

Latest traffic information

Breadcrumb Navigation

You are here:

  1. »
  2. Home »
  3. Road Projects »
  4. Area 3 »
  5. A34 Wolvercote Viaduct Replacement »
  6. About the Scheme

Website Navigation

Useful Links

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

How We Manage Our Roads

In this section you can find out more about how we manage and maintain these roads and plan for the future

The Project Control Framework

This framework sets out how we, together with the Department for Transport, manage and deliver major road improvement projects.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

About the Scheme

About the Scheme

The current proposal is for an on-line replacement of the existing viaduct. It will involve demolition of the existing viaduct in phases as follows:

  • Phase1 - construct a new temporary deck Southbound to the east of the existing structure
  • Phase 2 - demolish and remove the existing deck Northbound
  • Phase 3 - construct the new deck Northbound and demolish and remove the existing deck Southbound
  • Phase 4 - slide the new deck Southbound into position and stitch together