  4. M1 Junctions 21 to 31 Improvements »
  5. Contract 1: Junctions 25 to 28 »
  6. Contract 1: Junctions 25 to 28

Website Navigation

Useful Links

Feature

Better information for your journey

The National Traffic Control Centre collects real-time information on road conditions.

Quick Links

How We Manage Our Roads

In this section you can find out more about how we manage and maintain these roads and plan for the future

The Project Control Framework

On 1st April 2008 we launched the Project Control Framework. The Framework sets out how we, together with the Department for Transport, manage and deliver major improvement projects.

Traffic news on your desktop

Helpful ways to access the latest traffic information when you need it.

Contract 1: Junctions 25 to 28

Timetable

We appointed the contractor MVM in January 2007. The detailed design and planning work has been completed to allow construction work to start in October 2007.

The construction will be in stages. The first will be the section between Junction 26 and Junction 27. This will be followed by the remaining sections.

Details of closures and restrictions scheduled to be in place can be found on the Traffic Management page for this scheme.

Key dates

Please note that these dates are projections and are subject to change.

Event Date
Bridge widening, Junction 25 to Junction 28 (various locations) October 2007 to Autumn 2010
Vegetation Clearance Junction 25 to Junction 28 January 08 - March 08
Verge work Junction 26 to Junction 27 (to construct new lane) 27 January 2008 to Autumn 2008
Verge work Junction 25 to Junction 26 and Junction 27 to Junction 28 (to construct new lane) Autumn 2008 to Summer 2009
Central Reserve work Junction 25 to Junction 26, and Junction 27 to Junction 28 Summer 2009 to New Year 2010
Central Reserve work Junction 26 to Junction 27 New Year 2010 to Autumn 2010
Contract 1 motorway widening complete Autumn 2010

Historical Dates

Event Date
Entry into Targeted Programme of Improvements (Now known as Programme of Major Schemes) April 2004
Environmental Statement Published Spring 2006
Public comment/consultation for Contracts 1 and 2 March to June 2006
Public Exhibition Spring 2006
Contract Awarded to MVM Jan 2007
Ministers Decision to Proceed 6th August 2007

Start of Works Exhibitions:

Temple Centre, Nottingham Road, Nuthall, NG16 1DP
Risley Hall Hotel, Derby Road, Risley, DE72 3SS
Pinxton Village Hall, Kirkstead Road, Pinxton, NG16 6NA



Thursday 18 October 2007, 2pm to 8pm
Thursday 25 October 2007, 2pm to 8pm.
Saturday 27 October 2007, 10am to 3pm.
Contract 1 motorway widening work starts 29 October 2007; first major traffic management on the M1 January 2008.