Investigations

Completed inquiries

Greater Western Passenger Rail Franchise

current item indicator Administrative Timetable

Greater Western Passenger Rail Franchise

Administrative Timetable*

*Published on 7 November 2005 (and amended on 25 January 2006), in accordance with rule 6 of the Competition Commission Rules of Procedure. Revisions made to the timetable will be published on this web site.

30 September 2005

Merger references made

October – December

Gathering information, issuing questionnaires, hearing third parties

Mid-November

Publish statement of issues

Early December

Main party hearings

December

Verifying information, considering provisional findings

Early to mid-January 2006

Second main party hearing

20 January

Deadline for all parties’ responses/submissions required before provisional findings

Late January-early February

Notifying provisional findings
Notifying and considering possible remedies (if required)

Mid-February

Remedies hearing(s) (if required)

28 February

Final deadline for all parties’ responses/submissions

Early March

Publish report

16 March 2006

Statutory deadline for publishing report

 