National
Express Group / Thameslink / Great Northern Rail Franchise
Administrative Timetable*
*Published on 24 August 2005 (and amended on 2 November 2005),
as required by Rule 6 of the Competition Commission Rules
of Procedure. Any revisions made to the timetable will be
published on this web site.
| 3 August 2005
|
Merger reference made |
| Late August–early
September |
Gathering information, issuing questionnaires,
hearing third parties |
| 14 September |
Publish statement of issues |
| Late September |
Main party hearing
|
| September - October |
Verifying information,
considering provisional findings |
|
7 November |
Deadline for all parties’
responses/submissions required before provisional findings |
|
Week commencing 14 November |
Notifying provisional findings
Notifying and considering possible remedies (if required)
|
| Early December |
Remedies hearing(s) (if
required) |
|
Mid-December |
Final deadline for all
parties’ responses/submissions |
|
Late-December |
Publish report
|
| 17 January 2006 |
Statutory deadline |
|