Stena AB / P&O Inquiry
Administrative Timetable*
*Revised version, published on 18 November 2003, as required
by Rule 6 of the Competition Commission’s Rules of Procedure.
Any further revisions made to the timetable will be published
on this website.
22 August 2003 |
Merger reference made
|
August/September |
Gathering information, issuing
questionnaires, hearing third parties |
Early October |
Further third-party hearings
|
W/e 10 October |
Statement of issues
|
W/e 17 October |
Main party hearings with Stena and P&O
|
October/November |
Verifying information,
considering provisional findings |
Friday 7 November
|
Deadline for all parties’
responses/submissions required before provisional findings |
W/e 28 November
|
Notifying provisional
findings |
End Nov/early
Dec
|
Notifying and
considering possible remedies (if required) |
W/e 19 December
|
Remedies hearing/s
(if required) |
Friday 16 Jan
2004
|
Final deadline
for all parties’ responses/submissions |
End Jan/early Feb
|
Publish report |
6 February |
Statutory deadline
|
|