Firstgroup plc / Scotrail
Administrative Timetable*
| 13/1/04 |
Reference received |
| W/b 12/1/04 |
Gathering information
Questionnaires
Third party hearings
|
| W/b 19/1/04 |
| W/b 26/1/04 |
| W/b 2/2/04 |
| W/b 9/2/04 |
| W/b 16/2/04 |
| W/b 23/2/04 |
Further third party hearings;
Issues statement |
| W/b 1/3/04 |
Main party hearings |
| W/b 8/3/04 |
Verifying information
Consider provisional findings
|
| W/b 15/3/04 |
| Friday 26/3/04 |
Deadlines for responses/submissions
required before provisional findings; further hearings
if necessary |
| W/b 29/3/04 |
Verifying information
Consider provisional findings
|
| W/b 5/4/04 |
| W/b 26/4/04 |
Notifying provisional findings/possible
remedies (if required) |
| W/b 3/5/04 |
Remedies hearings (if required) |
| W/b 10/5/04 |
Final deadline for responses/submissions
from third parties |
| W/b 17/5/04 |
Final deadline for all responses/submissions |
| W/b 24/5/04 |
|
| W/b 31/5/04 |
|
| W/b 7/6/04 |
|
| W/b 14/6/04 |
|
| W/b 21/6/04 |
Statutory deadline 28/6/04¶ |
¶As noted in the CC’s General Advice and Information
(CC4), ‘in most cases the Commission expects to complete
its work in a shorter time than the maximum allowed’.
We hope that it may be possible to complete this inquiry earlier.
*Revised timetable, published on 22 April 2004, as required
by Rule 6 of the Competition Commission’s rules of procedure.
Any further revisions made to the timetable will be published
on this website.
|