Main Menu
- Other links
- Sections
- About
The study ‘Barriers to Commissioning Renewable Energy Projects’ was commissioned in June 2005. The study has collated evidence regarding the nature and scale of the post-planning approval delays. The report established the current position, likely future trends and recommended actions to speed up progress. It focused on barriers to commissioning onshore wind projects, however, it also addressed offshore wind, biomass and hydro projects.The Group commissioned a project which is looked at post-consent barriers to projects. The project is now complete and a presentation on the report and the way forward was discussed at RAB on 15 December 2005.
The analysis discovered that there are a number of factors leading to delays in the post approval phase of renewable energy schemes that are unlikely to improve without some form of intervention. The time taken to commission renewable energy schemes, following planning approval, is lengthening. A number of recommendations have been proposed to:
The report proposed 12 recommendations. An action plan to address the issues has been produced (RAB_2006_0005). A number of the recommendations are already being pursued, however, work will be commenced, and if appropriate additional studies will be commissioned, as soon as possible, on the following recommendations:
Recommendation 1 - Landowner negotiations & connection Wayleave Rights
The Law Society have been asked if they can facilitate this recommendation and progress will be reported to RAB in due course.
Recommendations 7&8 - Post approval decision making by determining authorities - Negotiating planning agreements and agreeing and discharging conditions.
This is an area of focus for the BERR's Renewable Deployment Team. A BERR funded study has collected and assessed a representative selection of planning conditions issued by regulatory bodies for wind energy schemes. The study will be used to inform next steps on implementing Recommendations 7&8.
Landowner easement and way-leave issues
Grid issues
Supply chain capability evaluation and support
Contracting structure developments
Planning condition guidance and timescales
Resources for planning across all layers of Government
Highlighting causes of delay to developers
Project economics and support for biomass
Further discussions to prioritise the recommendations and decide which ones to progress have been developed by a cross Department group, which will has produced an action plan to address the issues.
Objectives and work plans are for the remainder of 2006.
BERR working closely with RAB, Trade Associations and other stakeholders will take a number of the recommendations forward. This will form a part of BERR's work plan for the coming financial year, and the Working Group will act as a sounding board for future developments rather than pursue its own programme of activity.
In the remainder of 2006, the following activities will be progressed: