Friday began in a frenzy of activity, which would not have happened without everybody’s favourite crane operator LCpl Oldham. The panels weigh over 1.5 Tonnes so there were two options for LCpl Green and LCpl Patterson, physically lifting up the panels or LCpl Oldham’s crane, luckily the crane worked. There was obvious competition between the teams, LCpl Patterson’s team consisting of Spr’s Tansley and Chapman and LCpl Greens team consisting of LCpl Nash, Spr’s Clark and Jennings. The panel construction race between left and right side of bridge was very one sided early on however LCpl Green has managed to pull the deficit back with some interesting words of encouragement.
On Sunday our final load of containers arrived. It was another busy day for CPL “Paul” Ansell organising another seven container loads of bridge stores onto the yard.
At the moment we are building approximately 10 sections of bridge a day which takes some doing, and the lads are pretty tired at the end of the day. We are working six and half days a week so that we can get the bridge parts ready for the construction on time.
The bridge cost something like 3.5 million Dollars and they have not sent out the detailed plans, but that’s all part of the fun. Anyway it will soon be time for the construction across the Shatt-Al-Arab this is when it will get really different. More on that next time Happy Christmas to you all.
Story by LCpl Skivington